1 | Project Name | Tourism - MMP |
2 | Project Cost | Rs. 11,45,000/- (Agreement Cost) Rs. 21.35 Crore for five years- DPR Cost |
3 | DIT Share | - |
4 | State Share | - |
5 | Duration | 12 Weeks |
6 | Release | Payment made by Capacity Building A/c as per Letter No 720/ITDA-129 Dt. 17-11-2007 |
7 | Date of Advertisement/ Name of Papers |
04-04-2007 Amar Ujala, Dainik Jagran, The Times of India, Hindustan Times, Economic Times Corrigendum 22-04-07 Amar Ujala, Dainik Jagran, The Times of India, Hindustan Times, Economic Times |
8 | Detail as RFP | RFP assesed to 08 shortlisted and firms as per following: Send To: 1- M/s SREI New Delhi 2- M/s TCS Lucknow 3- M/s Deloitte New Delhi 4- M/s Wipro Ltd. 5- M/s Price Water House Coopers Pvt. Ltd., 6- M/s 3 I Infotech Ltd, New Delhi 7- M/s TCIL New Delhi 8- M/s Ernest & Young Pvt. LTd. Gurgaon |
9 | Date of Tender | RFP agreed on 28-02-08 No. ITDA/ NeGP-MP/Tourism/ 2007 |
10 | No. of Tender Received/ Name of the Firms |
RFP received only 04 firms as per following: 1- M/s Deloitte New Delhi 2- M/s Wipro Ltd. 3- M/s Price Water House Coopers Pvt. Ltd., 4- M/s 3 I Infotech Ltd, New Delhi |
11 | Date of Opening of Tender |
08-05-2008 (commercial bid evaluation) |
12 | Selection of Consultant |
M/s Wipro |
13 | Bid Value | Rs. 11,45,000/- |
14 | Agreement with Consultant |
M/s Wipro vide letter No. 05/Preparation of DPR for Tourist Deptt/ ITDA/ GoU/ 2008 Dt. 07-08-08 |
15 | Duration of Agreement |
12 weeks |
16 | Mile Stone of Agreement |
1- Advance against BG valid for 12 months (20%) 2- Submission of the "Scope and AS-IS assment report" finalised after the First Departmental Workshop and its approval (15%) 3- Submission of the "Report of GPR and TO-BE process Maps" finalised after the second departmental workshop and its approval (20%) 4- Submission of the Detailed Project (DPR) (20%) 5-Acceptance by Govt. of Uttarakhand (10%) 6- Acceptance by GOvt. of India/ Funding Agency (15%) |
17 | Completed Mile Stone | 1- Advance against BG valid for 12 months (20%) 2- Submission of the "Scope and AS-IS assment report" finalised after the First Departmental Workshop and its approval (15%) 3- Submission of the "Report of GPR and TO-BE process Maps" finalised after the second departmental workshop and its approval (20%) 4-Submission of the Detailed Project (DPR) (20%) 5- Acceptance by Govt. of Uttarakhand (10%) |
18 | Payment to Consultant | Rs. 9,73,250/- |
19 | Pending Bill/ Liabilities of Consultant |
|
20 | Meeting regarding project, Agenda & Minutes in Chronological Orders | |
21 | Present Status | DPR sent by UTDB to GoI for funding |
22 | Action Needed | Followup by Deptt of Tourism at GoI to funding |
23 | Remark |